Role of Architectural drawing for Execution

Project:www.sefindia.org
Component:Miscellaneous
Category:support request
Priority:normal
Assigned:arumugampb
Status:active
Description

Dear Sefians

I had given a structural drawing to contractor for execution of 1st floor
beam and slab. There was one cutout in the slab, it was misplaced to next grid in structural drawing with respect to architectural drawing.

Now the slab is cast and the contractor is telling, he has not referd relavant architectural drawing for slab cast.

Now my question is it required whether the contractor should follow and corelate both strucutral and architectural drawings at the time of each stage of execution or not ?

Clarification and comments are required from Sefians

Regards
Aru

Updates

#1 submitted by s_vijaykumar on Mon, 05/13/2013 - 09:44

Cutout etc details shall be shown in RCC drawing and no way contractor is responsible to follow architectural drawings when he is doing RCC work.