View previous topic :: View next topic |
Author |
Message |
kajal.chopra ...

Joined: 26 Jan 2003 Posts: 102
|
Posted: Tue Dec 30, 2008 10:01 am Post subject: |
|
|
See Kedar,
in your point no 1 you have arrived at the shear going to the column 13.13 KN by distributing the total shear in proportion to the stiffnesses of column and slab.Right?
My question is that if the slab and column are cast in two different operations, can we distribute the total shear in proportion to the stiffnesses of the slab and column?
Distribution of shear in proportion to stiffnesses is valid only if a complete monlolthic action exists between slab and column.Right?
Now, if the two that is slab and column are cast in 2 separate operations, can there be a complete monloithic action ensured between the two? |
|
Back to top |
|
 |
Kedar SEFI Regulars

Joined: 23 Jul 2008 Posts: 32 Location: Mumbai
|
Posted: Tue Dec 30, 2008 10:26 am Post subject: |
|
|
Hi Kajal
If the joint is NOT monolithic one can not
distribute shear in proportion with stiffness.
But therotically if the slab is forced fit one can expect
slight constraint for deflection of column,hence there
could be transfer of shear in the form of push/pull
to slab.
This is similar to concept of introducing stiffness reduction factor for
joint as a whole,hence shear distribution procedure won't change i.e. if there is absolutely no connection between slab and column the stiffness reduction factor will become ZERO and factor will become ONE if there is monolithic connection giving us previous results.
But Practically its less important.
regards
Kedar |
|
Back to top |
|
 |
amarjeetsingh ...

Joined: 09 Nov 2008 Posts: 130
|
Posted: Thu Jan 01, 2009 8:21 am Post subject: Post tensioned slabs |
|
|
dear all,
lots of informative tech material about PT/ Conventional Flat slab has been discussed in the last fewdays in this forum. it will be appreciative if the material is complied and posted as reference for all of us.
thanks in anticipation
regrds
amarjeet singh
On 12/30/08, Kedar <forum@sefindia.org (forum@sefindia.org)> wrote: Quote: | Hi Kajal
If the joint is NOT monolithic one can not
distribute shear in proportion with stiffness.
But therotically if the slab is forced fit one can expect
slight constraint for deflection of column,hence there
could be transfer of shear in the form of push/pull
to slab.
This is similar to concept of introducing stiffness reduction factor for
joint as a whole,hence shear distribution procedure won't change i.e. if there is absolutely no connection between slab and column the stiffness reduction factor will become ZERO and factor will become ONE if there is monolithic connection giving us previous results.
But Practically its less important.
regards
Kedar
|
Posted via Email |
|
Back to top |
|
 |
rbchopda SEFI Member

Joined: 30 Aug 2008 Posts: 6
|
Posted: Thu Jan 01, 2009 2:12 pm Post subject: Post tensioned slabs |
|
|
Dear sir,
very good suggestion, i strongly support this.
Regards
er.rbchopda@rediffmail.com (er.rbchopda@rediffmail.com)
On Thu, Jan 1, 2009 at 3:29 PM, amarjeet singh <forum@sefindia.org (forum@sefindia.org)> wrote:
[quote] dear all,
lots of informative tech material about PT/ Conventional Flat slab has been discussed in the last fewdays in this forum. it will be appreciative if the material is complied and posted as reference for all of us.
thanks in anticipation
regrds
amarjeet singh
On 12/30/08, Kedar forum@sefindia.org (forum@sefindia.org))> wrote:
--auto removed--
Posted via Email |
|
Back to top |
|
 |
Dr. N. Subramanian General Sponsor


Joined: 21 Feb 2008 Posts: 5435 Location: Gaithersburg, MD, U.S.A.
|
Posted: Thu Jan 01, 2009 4:09 pm Post subject: Post tensioned slabs |
|
|
Dear all,
I
t is a good suggestion by Mr. Amajeet Singh. As I indicated in my earlier email, a special publication similar in line with ACI Special publication, may be compiled, with some design examples of both RCC and PT slabs and also idealization of flat slabs for computer analysis, etc. The document may be posted in SEFIndia site and published as a book.
Regards
Subramanaian
Dr.N.Subramanian,Ph.D.,F.ASCE, M.ACI,
Consulting Structural Engineer
Maryland, USA
See my books at: www.multi-science.co.uk/subramanian-book.htm
www.oup.co.in/search_detail.php?id=144559
--- On Thu, 1/1/09, amarjeet singh <forum@sefindia.org> wrote:
[quote]From: amarjeet singh <forum@sefindia.org>
Subject: [ECONF] Re: Post tensioned slabs
To: econf@sefindia.org
Date: Thursday, January 1, 2009, 3:29 PM
dear all,
lots of informative tech material about PT/ Conventional Flat slab has been discussed in the last fewdays in this forum. it will be appreciative if the material is complied and posted as reference for all of us.
thanks in anticipation
regrds
amarjeet singh
On 12/30/08, Kedar forum@sefindia.org)> wrote: --auto removed--
Posted via Email |
|
Back to top |
|
 |
Rajiv Diamond Sponsor


Joined: 04 Aug 2008 Posts: 52
|
Posted: Mon Jan 05, 2009 1:08 pm Post subject: Post tensioned slabs |
|
|
Dear Mr. Bhowmick, Mr. Garg and Dr. Kalgal:
Many thanks for discussing so many things in one single post. Staged analysis is important in many rapid projects where a time cycle is defined for use and reuse of forms. The only way of doing it is to consider time dependent material behaviour in solving the problem. Linear analysis software can't handle this complex problem.
However there are many software available which can do this. For example, SAP2000 and Adina for staged analysis. PT slabs can be designed using SAFE P/T, ADAPT, RAPT etc.
Thanks and regards
Rajiv
On Sun, 28 Dec 2008 PRADEEP GARG wrote :
Quote: | Dear Mr. Alok Bhowmick & Mr Kalgal
Thanks for discussing some very pertinent question and answers on Flat Slabs and PT slab.
I have one more querry in this regard :
The modelling of slab-beam-column-shear wall structures for analysis and design is quite well known when using softwares like STAAD, E-Tabs etc.
How should flat slab- column -shear wall be modelled in these softwares for analysis and design ?
Pradeep Garg
--- On Thu, 12/25/08, bsec <forum@sefindia.org> wrote:
Quote: | From: bsec <forum@sefindia.org> Subject: [ECONF] Re: Post tensioned slabs To: econf@sefindia.org Date: Thursday, December 25, 2008, 5:26 PM
Dear Mr Kalgal,
Thanks very much for such a crisp and prompt
| response. It answers my querries to a large extent
Quote: | Alok Bhowmick
-----Original Message----- From: mkalgal [mailto:forum@sefindia.org] Sent: Thursday, December 25, 2008 4:43 PM To: econf@sefindia.org (econf@sefindia.org) Subject: [ECONF] Re: Post tensioned slabs
Dear Alok
A very big list indeed!
Will try to answer as briefly as possible
1. What are the key benefits of Flat Slab
| construction vis-à-vis a normal beam and slab construction?
Quote: | a. Absence of beams leads to greater head room. b. For a given head room (which in case of beam slab
| construction is to the soffit of the beam), the storey height can be reduced, which leads to lesser weight on columns and foudation, reduction in cost of walling, plaster and painting etc. (If we can reduce 300mm in each floor, you get one floor more for the same height as would be required for a 10 storey beam-slab buliding!)
Quote: | c. You can have floor height windows since there are
| no beams
Quote: | d. Since Shuttering is simpler, it takes less time to
| provide and remove shuttering (mentioned in your question 3).
Quote: | e. Bar-bending work is simpler
2. When and under what circumstances one should
| decide to go for Flat Slab Construction for a given project? What is the economic span range for flat slab construction? Is there any guideline?
Quote: | First part is answered above. Economical spans depend
| on the loading and number of spans. In RCC, flat plate/slabs are provided between 6m to 10m spans. It can be shown that PT slabs are more economical than RC Flat slabs for spans between 9m and 12m spans.
Quote: | Do not ask for a flat slab to be more economical than
| beam-slab! Beams slab construction is generally more economical and robust as compared to flat slab systems.
Quote: | 3. Post Tensioning of Flat Slab helps not only to
| bring in material economy in the structure, but also helps to speed up construction as the de-shuttering can be done much faster. Is it a practice in India to go for RCC Flat Slab (rather than PT Slabs?).
Quote: | There are hundreds of PT flat slab building built and
| hundreds more are being built. There are more than 6 PT companies working all over India and their hands are full.
Quote: | Some consultants prefer RC flat slabs over PT flat
| slabs, more so in seismic zones IV and V. Nothing wrong in it, but my personal opinion is if RC flat slab is OK; there should be no bar for PT flat slabs in these zones.
Quote: | In-fact, since PT flat slabs are slightly less thick
| than RC flat slabs, the seismic mass is lesser and the seismic demand on the system reduces.
Quote: | 4. For a typical multistoried building, What would be
| the time saving with Flat Slab? Is there any cost saving also in case one goes for Flat Slab construction? Specific case study, if done for Indian projects may be shared by experts in the field.
Quote: | Construction companies/consultants could come out
| with cost-cmparison studies that they would have.
Quote: | 5. What are the pre-requisites for Flat Slab
| Construction, in terms of geometry of the multistoried building design that the architects must know. Is there any documented guideline in this regard?
Quote: | There are no rigid pre-requisites as per codes. It is
| preferable to have regular column disposition so that if one wants to use a equivalent frame method (EFM) to cross check his finite element method (FEM), it would be simpler. But column positioning is many a times usurped by architects! Just like it is better to have a symmetrical building in terms of geometry and mass from seismic resistance criteria - but how many architects care? A typical reply - "you can't curtail my freedom for creative designs!" I have suggested in my mails in this and other sections some useful articles to read.
Quote: | 6. Upto what span length, RCC Flat Slab is economical,
| beyond which one should go for PT Slabs in India. What is the maximum span length upto which one can go for Flat Slab with PT.
Quote: | Answered under question 2 above. As for maximum span, it is a function of loading,
| number of bays, the thickness that one is ready to provide and so on. The company where I worked had provided 12m to 14m spans in many buildings. When moments become difficult to handle, we would provide PT band beams between the columns
Quote: | 7. For a PT Flat Slab, what are the various methods
| of post tensioning which are available in India? Any guideline?
Quote: | In India is invariably bonded post-tensioning that is
| adopted. A comparison between bonded and unbonded PT is given in an article of mine which I had written a few years ago and have appended it with this mail.
Quote: | As for guidelines, many are available abroad (on the
| internet as well) and proposed IS 1343 (a draft is enclosed with one of my replies in this E-conf) also attempts to give some guidelines.
Quote: | 8. What is the choice of design methods for Flat Slab
| Construction?
Quote: | Please see my article appended.
9. I am aware that there are softwares (like ADAPT),
| which are available for design of Flat Slab. Are these softwares applicable for Indian Projects, where one has to follow the Indian codes?
Quote: | There are many softwares with IS code modules fitted
| in.
Quote: | 10. How important is the construction stage check for
| Flat Slab? Rapid construction, I believe can lead to loading of slab at a time when it has not gained the full strength! Is it a practice to carry out construction stage check and is it a governing load case ?
Quote: | Yes. In PT slabs, the shutters are removed
| immediately upon stressing, which is about 3-4 days. Although it is re-propped, many a times the props are inadequate. We must make sure that the props are adequate and stay put for the required number of days or else do a construction stage analysis. This can be critical since there is chance of the live load to dead load ratio being lesser in long-span flat slabs. Also since the speed is so high (one slab every 6-10 days) the second slab below would receive loads from two floors higher and if not supported, could fail.
Quote: | Hope this answers the curiosity to some extent!
regards
Kalgal
Attachments: PT in Building Sector.pdf (http://www.sefindia.org/for-
| um/files/pt_in_building_sector_839.pdf)
|
Posted via Email |
|
Back to top |
|
 |
|
|
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum You can attach files in this forum You can download files in this forum
|
|
|