www.sefindia.org

STRUCTURAL ENGINEERING FORUM OF INDIA [SEFI]

 Forum SubscriptionsSubscriptions DigestDigest Preferences   FAQFAQ   SearchSearch   MemberlistMemberlist   UsergroupsUsergroups  RegisterRegister FAQSecurity Tips FAQDonate
 ProfileProfile   Log in to check your private messagesLog in to check your private messages   Log in to websiteLog in to websiteLog in to websiteLog in to forum 
Warning: Make sure you scan the downloaded attachment with updated antivirus tools  before opening them. They may contain viruses.
Use online scanners
here and here to upload downloaded attachment to check for safety.

Field Engineering Talks on FB and Others
Goto page Previous  1, 2, 3 ... 130, 131, 132 ... 150, 151, 152  Next
 
Post new topicReply to topic Thank Post    www.sefindia.org Forum Index -> SEFI General Discussion
View previous topic :: View next topic  
Author Message
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:20 am    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Telecommunicati Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Telecommunication Scope of Work and Supply+Hotline Telephone System
Chapter 8

Building Design Concept
Chemical Plants
Hotline Telephone System     
1     For details of guideline specification, refer specification for Hotline Telephone System document # …and system diagram Hotline System drawing #.
2     Hotline telephones shall be installed between CCR in CB to two (2) new customer sites associated with LLCCS LNG-1 and LNG-2.  
3     Provision of hotline telephone service shall include telephones and PCM FXO / FXS circuits.
4     Existing hotline console at CCR shall be upgraded to accommodate new handsets and indicators, refer hotline console layout drawing #.....
5     In event, when customers sites are not available at commissioning time then commissioning shall effect at applicable LLCC.
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:21 am    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Telecommunicati Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Telecommunication Scope of Work and Supply+Telephone & Data System
Chapter 8

Building Design Concept
Chemical Plants
Telephone & Data System
1     For details of guideline specification, refer, specification for telephone system document #......  
2     A PABX, Ericsson model MD 110 exists at PAB and all telephone users at existing LLCCS and at intake area, operate as remote subscribers via FXS / FXO circuits on SDH optical transmission system.
3     In 2nd quarter 2006 a PABX shall be provided by others at CB
4     Therefore, all new LLCCS shall operate, as remote subscribers from PABX at CB and all users in intake area could operate as direct subscribers.
5     PABX at CB shall have sufficient capacity, duly equipped for all new subscribers in intake area and remote subscribers at LLCCS
6     Active components of data network shall be supplied by others and LAN would be commissioned by others.
7     All cables, structured cabling, IDFS, junction boxes, interfaces, interconnections etc. to affect a comprehensive infrastructure shall form part of this scope of work.
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:22 am    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Telecommunicati Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Telecommunication Scope of Work and Supply+Telephones, Fax Machines and Audio Mux
Chapter 8

Building Design Concept
Chemical Plants
Telephones, Fax Machines and Audio Mux
1     For details of guideline specification, refer specification for telephones and fax machines document # ……….
2     All telephone shall have RJ-45 connectors and types of telephones installed should be different for different areas and functions, as tentatively defined on drawings and relevant documents.
3     Refer to equipment list telecommunication equipment, document #… for quantities.
4     All fax machines model L-360 or later version from Canon or equivalent shall have RJ-45 connectors to be installed in locations tentatively, defined on drawings documents, with four (4) audio mux with FXO / FSX capability would be required to provide individual telephone communications over dual optical fibre between PABX at CB and LLCCS.
Earthing
1     All telecommunication equipment shall be connected to telecom earth at existing stations and a separate telecom clean earth of less than one (1) ohm at each new location.
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:27 am    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Telecommunicati Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Telecommunication Scope of Work and Supply+Power Supplies+Miscellaneous
Chapter 8

Building Design Concept
Chemical Plants
Power Supplies+Miscellaneous
1     A fully redundant nominal - 48VDC battery / charger system with 8 hours autonomy shall be provided and used to supply all telecommunications related equipment at LLCC MOV Corridor H.
2     Battery / charger system shall be designed in accordance with datasheet DC UPS document # …in order to supply power to telecommunication equipment and shall have 50% spare capacity.
3     A fully redundant nominal -48VDC battery / charger system with nominal 8 hours autonomy shall be provided by others and used to supply all telecommunications related equipment at fire station.
4     PDH and associated equipment at fire station shall connect to this existing supply.
5     A fully redundant nominal -48VDC battery / charger system with nominal 8 hours autonomy, exists at each node in SDH / PDH optical transmission system and can be utilized for like equipment.
6     Each new site shall contain a 230 V AC UPS, which shall be utilised for all new PA/GA equipment.

Testing
1     Testing shall be conducted in order to demonstrate specifications of equipment, subsystem / system have been achieved and as stated, in applicable system specifications.

Training
1     Training shall be provided, as stated in applicable system specifications in appendix  and is to be conducted at site.
2     Training shall be as conducted, per manufacturer’s standard syllabus and should be conducted by manufacturer.

Documentation
1     Documentation shall be provided for design, purchase, installation, as built and O&M phases ,as stated in applicable system specifications in relevant appendix.
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:29 am    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Telecommunicati Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Telecommunication Scope of Work and Supply+Security System
Chapter 8

Building Design Concept
Chemical Plants
Security System
General          
1     Security system for plant industrial city shall be highly confidential.
2     Details shall not be reproduced or / and copied.
3     Contractor shall provide a security system for intake area, along pipeline corridor and at receiving basin (RB).
4     Refer specification for security control system, document #.., closed circuit television system diagram, drawing #.., card access control system diagram, drawing #.., field location layout security system, drawing #.. and equipment layout security system drawing # …..
5     Contractor is required to make itself fully aware of all relevant standards and regulations, including company / client standards, base its design and installation on those standards and regulations.
6     Contractor shall note that company / client standard, cable infrastructure standards of IT department is vendor limited in some cases and therefore, shall not be issued to vendors.
7     Contractor shall ensure that entire security works shall be carried out through a qualified Security & Telecommunications systems integrator.
8     Contractor and systems integrator shall attend, liaison, review progress meetings in nation on a monthly basis, during design phase and weekly site meetings, during construction phase.
9     Monthly meetings, during design phase to be conducted for a period of 3 days and shall also, include site visits.
10     Company / client, at its discretion, may choose to conduct certain monthly meetings via teleconference.
11     Weekly meeting during construction phase to be conducted for a limited period, as required and shall include a joint inspection of work conducted at that time.
12     Company / client shall agree to combine Telecommunications Meetings with those of security in event, same system integrator is chosen.
13     Contractor shall study and revalidate FEED, both as a desktop exercise and via a number of site visits to be conducted, during initial stage of project to familiarize and study Telecommunication System implemented as well as, changes being implemented within plant city.
14     Contractor shall make four (4) site visits for a period of two (2) full days each visit.
15     Company / client shall agree to combine telecommunications site visits with those of security in event, same system integrator is chosen.
16     Contractor shall suggest, whatever enhancements with rational explanation to FEED following FEED verification in form of a report for approval of company / client.
17     Contractor shall submit for approval of company / client, site visit reports for each site visit.
18     Contractor shall provide load analysis on existing power supplies that shall be directly utilized, as part of this project and provide a report with rational explanation and recommendations, after having considered all alternatives.
19     Contractor shall be aware that existing CCTV system at plant is in process of being upgraded to an IP Ethernet based network and this is due for completion.
20     Coverage of existing and upgraded system does not include location areas that form part of this scope of work.  
21     All systems shall be provided fully assembled, supplied, configured and tested, in accordance with relevant project specifications.
22     Also, contractor shall be responsible for interfacing new systems with existing telecommunication systems, whatever up grade work required on hardware / software of existing system for this purpose shall be carried out by contractor.
23     Contractor shall obtain prior approval from company / client of its detailed design, before proceeding with purchase of equipment and installation work.
24     Contractor shall participate in a formal design review in Nation, six (6) weeks, prior to purchase of equipment and include appropriate company / client comments in design.
25     Contractor shall ensure adequate coordination, between security system integrator and all other disciplines / activities on site, conducted in order to ensure an efficient installation.
26     Contractor shall perform following scope of work:
a     Provide a new CCTV system consisting of cameras, hubs / switches and monitors interfacing to an upgraded existing CCTV System.
b     Provide a card access control system (CACS) at gate house # ..and gate house # ..to automate inbound / outbound vehicle & personnel movements.
c     Provide security fencing and lighting around intake facility.
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:30 am    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Security System Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Security System+Security System Specifications & Datasheets
Chapter 8

Building Design Concept
Chemical Plants
Security System
Security System Specifications & Datasheets
1     Contractor shall generate a standalone detailed specification and / or datasheet for each security system, subsystem and equipment.
2     These documents shall be regularly, updated until as built stage is reached.
3     Specification shall cover complete details of selection of type, materials, requirements pertaining to manufacturing, QA, QR / QC, inspection, painting, storage, handling, transportation and operations & maintenance etc.
4     Contractor shall use specification for security control system, document #.. as an initial basis of specifications to be developed.
5     Specifications shall be submitted to company / client for approval.
6     Contractor shall ensure that every element in system shall have an associated mean time between failure (MTBF) of better than 20,000 hours and that each subsystem shall have a mean time to repair (MTTR) of better than two (2) hours, assuming appropriate spare part is available.
7     Availability of system shall be 99.999 %
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 10:49 pm    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+AnnexSL Reply with quote

42 Minutes Video
22.09.2021-Civil Field Engineering + Life + Quality AnnexSL + COVID-19 + SHE+ Engineers Role + Designs + Construction + Methods + Contracts + Organisations + Communication + Coordination + Why be behind Quality of Standard Material + Works? Talk 511
https://www.facebook.com/100000185425294/videos/143968641275221
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Tue Sep 21, 2021 11:13 pm    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality Reply with quote

7 Minutes Video-Interrupted by signals break
22.09.2021-Civil Field Engineering + Life + Quality AnnexSL + COVID-19 + SHE+ Engineers Role + Designs + Construction + Methods + Contracts + Organisations + Communication + Coordination + Why be behind Quality of Standard Material + Works? Talk 512
https://www.facebook.com/pesuraj/videos/382333246892197
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Wed Sep 22, 2021 10:46 pm    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Security System Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Security System+Closed Circuit Television (CCTV) System
Chapter 8

Building Design Concept
Chemical Plants
Closed Circuit Television (CCTV) System
Scope of Work and Supply
1     CCTV system shall include PTZ (pan / tilt / zoom) cameras at intake area, pipeline corridor and receiving basin (RB) together with fixed cameras, with alarm capability to accommodate provision of motion detection facilities around perimeter of intake area.
2     All cameras shall be IP standard.
3     Company / client is in process of evaluating, whether or not, to proceed with motion detection in intake area and consequently, security field layout drawing #... show layouts, with and without motion detection.
4     There shall be a combination of fixed focus cameras and PTZ dome type cameras around fence of intake area to provide a system capable of motion detection.
5     Only PTZ dome type cameras shall be utilised for a system ,with no motion detection.
6     In both systems, additional  PTZ cameras for enhanced monitoring, within intake area shall be installed
7     Refer equipment list telecommunication equipment, document #... for quantities.
8     Contractor shall state in appendix, price reduction should motion detection not be implemented.
9     There shall be two (2) PTZ dome type cameras, installed at each pipeline corridor and RB.
10     Three (3) new monitors shall be installed in CCR in existing CB.
11     Signals from all cameras in intake area shall be available on these monitors.
12     These signals shall also, be monitored at four (4) new monitors located in plant CR at Main Gate House (MGH) via existing upgraded CCTV network.
13     System control shall be conducted from existing upgraded CCTV system.
14     Signals from CCTV cameras at pipeline corridor and receiving basin (RB) shall be monitored / controlled by existing upgraded CCTV system from plant CR at MGH.
15     Existing SDH optical transmission system shall be upgraded with Ethernet modules to provide CCTV camera(s) signal transport from intake area, LNG2 and receiving basin (RB) to CCTV monitors at CCR CB and CR plant at Main Gate House and to existing network video recording system at plant CR at MGH, which shall be upgraded to accommodate additional data to be received.
16     Existing upgraded CCTV System management shall be further upgraded, including software configuration in order to connect and activate peripherals e.g. cameras and monitors, as required to ensure a seamless integration of CCTV system at intake area, pipeline corridor and RB.
Back to top
View user's profile Send private message Visit poster's website
suraj
General Sponsor
General Sponsor


Joined: 17 Apr 2008
Posts: 3554
Location: NCR Faridabad, E mail suraj_engineer@yahoo.co.uk

PostPosted: Wed Sep 22, 2021 10:48 pm    Post subject: Field Engineering Building+General+Soil+FIDICSilver-Quality+Design General Specification+Chemical Plant +Security System Reply with quote

Buildings Practice Facilities Plants-Petrochemicals+Quality+Design General Specification+Chemical Plant +Security System+Card Access Control System (CACS)
Chapter 8

Building Design Concept
Chemical Plants
Card Access Control System (CACS)
1     CACS shall be a standalone system, installed in gate houses of intake area.
2     Separate controllers shall be installed in each Gate House, integrated together in order to provide redundancy for each gate house.
Access control system shall have following facilities:
a     Card readers to enable in-bound and out-bound vehicle and personnel traffic.
b     Vehicle gates, turnstile gates, automatic opening and closure of vehicle gates and turnstiles
c     Controlled access by pre programmed access card(s) or by security personnel access control.
d     Recording of time and date of in-bound and out-bound movement.
e     Card readers shall be compatible to existing CACS being used at main gate.
Back to top
View user's profile Send private message Visit poster's website
Display posts from previous:   
Post new topicReply to topic Thank Post    www.sefindia.org Forum Index -> SEFI General Discussion All times are GMT
Goto page Previous  1, 2, 3 ... 130, 131, 132 ... 150, 151, 152  Next
Page 131 of 152

 

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum
You cannot attach files in this forum
You can download files in this forum


© 2003, 2008 SEFINDIA, Indian Domain Registration
Publishing or acceptance of an advertisement is neither a guarantee nor endorsement of the advertiser's product or service. advertisement policy