Posted: Fri Jun 29, 2018 4:06 am Post subject: Option for Boulder replacement |
|
|
Good Morning Respected Sir;Madam,
Need some opinion about the condition facing at the site...Need some alternatives for the said condition
1) Total Dead weight of the machine is 13 tons approx.
2) When the machine is in the loaded condition ie when applied pressure the dead weight of the machine remains the same.
3) Total Capacity of the machine is 40 Tons (Hydraulic Force)
4) Anti-Vibration pads are provided at the base of the machine.
Further we require from you the details as below;
1) Foundation structure Load calculations.
2) For foundation slab,boulders are provided as base ,however as pit to be constructed in confined area where compaction of boulder is not possible,alternate arrangement of equal strength such as PCC should be proposed. |
|